Construction Update Q1 2026
March 2026 Drone Footage Captured by Ashley Albert
Over the past couple of months, things have truly come together, and we’re thrilled to see the finish line in sight. Thank you to everyone who has supported The Beacon Project along the way. It’s been a long journey, and we’re excited to share how far we’ve come and what’s ahead.
Administration Building:
December 2025 - Cabinets were installed and generously donated by Chandler Cabinets.
February 2026 - 16,000 sq ft Administrative & Therapy Center is finished and fully operational! The community gathering and training room is equipped with modern technology for the Knowledge Center. High‑quality furnishings installed, sourced at a significantly reduced cost.
32-stall Barn:
Barn construction progressing, with full project completion on track for Q2 2026!
Other:
Landscaping: Decomposed granite installation between event space and arena, irrigation prep underway.
Special event plaza completed with turf, shade sails, A/V, and landscaping.
Second arena completed, serving as a temporary barn to sustain operations.
Parking and grading - projected start date is early April 2026.